Period
February 2014 – November 2014
Location
Rumaila Oil Field, Iraq
Client
SIPD/CCC

SCOPE OF WORK

The work includes but not limited to;

  • Fabrication and Installation piping and UG pipe line
  • Installation and commissioning  the Electrical works .
  • Installation all the Instrumentation Panels , Cables and Instruments ,etc…
  • NDT Works
  • Painting testing
  • Hydrostatic test .
  • Testing and commissioning