Period
January 2012 – June 2013
Location
Badra Oil Field , Iraq
Client
Petrofac Limited

SCOPE OF WORK

The work including but not limited the following :

  • Design , fabrication and installation and testing piping system .
  • Supplying all missing materials such as ( pipes , fitting , flanges , valves , etc…)
  • Sand blasting and painting all the fabricated piping system .
  • Supplying , fabrication and installation all kind of steel pipe supports .