Period
November 2015 – December 2016
Location
Badra Oil Field , CPF Phase 2
Client
Gazprom/Samsung Engineering
SCOPE OF WORK
The work including the below activities :
- Installation of Rotating Equipment (High/Medium Gas Compressor (6 Units), Horizontal & Centrifugal Pumps, Electrical Crane, Installation of Stationary Equipment (Vessels, Drums, Columns, Heat Exchangers, Filters).
- Fabrication and Installation of Storage Tanks.
- Hydrostatic Testing and Cleaning Services
- Fabrication and Installation of Piping Systems (CS, SS, Alloy Steel)
- Launcher and Receiver Fabrication and Installation
- Installation of Valves and Other Piping Elements
- Sandblasting, Panting and Coating Services
- Hydro Testing Services
- Flange Torqueing and Bolt Tightening
- Installation MV,HV,LV panels and Transformer
- Installation power and control cables
- Installation and commissioning the instrumentation works